Dagenham Park CofE School completed in just 16 weeks

Dagenham Park

The McAvoy Group has now completed the handover of Dagenham Park Church of England School. The brand new, stand-alone, two-storey permanent modular teaching facility had a total project time of just 16 weeks, from factory to handover.

As principal contractor McAvoy were responsible for the detailed design and installation of the project, with installation of the modules taking just three days. Working in partnership with the London Borough of Barking & Dagenham, McAvoy ensured the project was delivered within the allocated programme.

The brand new building comprises 13 classrooms in total, WC facilities, stores, circulation areas, cloakrooms, an IT hub, offices and a group room.

Dagenham Park

Dagenham Park Dagenham Park